Engineering

Scio Church Road Improvement Project

Skip Navigation LinksHome » Departments » Engineering » Scio Church Road Improvement Project
 

Parking removal discussion update​​

The Transportation Commission recommended (October 21, 2020) and City Council approved (November 16, 2020) the prohibition of On-Street Parking on the north side of Scio Church Road between South Maple Road and Greenview Drive.

To continue building upon the City's Non-motorized plan, on-street bicycle lanes will be implemented where the parking is removed. Scio Church is a key link for bicyclists riding between this area and downtown.

Find additional materials related to the parking removal discussion in the 'Documents' section below. ​

Project background

During the summer of 2021, Scio Church Rd., between South Maple and South Seventh St., will be improved.  Some watermain service and hydrants will be relocated, stormwater management will be installed and the road will be resurfaced. ​

Timeline

Tentative Construction Schedule: 
September – November 2021 (S. Maple intersection, water main transfers, and concrete work)

April – June 2022 (milling and paving)​

The 2021 work will require a detour and allows for only one lane of eastbound traffic between S. Maple and S. Seventh, whereas the 2022 work will not require a detour and one lane in both directions will be maintained under traffic control.​

Project limitsScio Church Road project map image.png

  • ​​Scio Church Road between S. Maple Road and S. Seventh Street

Why is this project being done?

Some existing water service and hydrants are on existing water mains that are undersized and require repair.  These leads will be transferred to the larger water main across the street.   Also, the current condition of the pavement is poor and in need of replacement.

​Work to be done:​

  • The existing water main leads will be relocated to the larger water main to increase capacity.

  • The existing pavement will be replaced from S. Maple to S. Seventh.

  • Some existing curb, sidewalk and ramps will be replaced for Americans with Disabilities Act (ADA) compliance.

  • Some storm water improvements will be done throughout the project, as well as within the median between Scio Church Road and the service drive between Greenview Drive and S Seventh Street similar to the median east of S Seventh Street.

  • Some safety improvement features will be installed including new bike lanes, filling sidewalk gaps, and installing new crosswalks. Three new crosswalks will be installed in between Covington and Old Pear Tree Ct, near Churchill Drive, and near Mershon Drive. In addition, a connection sidewalk between Yeoman Court and Scio Church will be installed.

  • Plans submitted to M​DOT (PDF) 

Possible impact to residents:

  • Scio Church Road will be closed to through traffic for the duration of the construction.  Driveway access for local traffic will be maintained, but may include delay during working hours.  Cross street traffic will be maintained as much as possible.

  • Water service will be interrupted for short durations during water main relocation for a few residents. Disruptions will be limited, and residents will be informed in advance. 

  • General noise and dust from equipment, particularly during site excavation.​

Costs and funding source

City Street, Bridge, and Sidewalk Millage, Federal Funding, Storm Utility Funds, and Drinking Water Funds will fund the majority of the work on this project.  New sidewalks adjacent to taxable properties will be funded by the New Sidewalk Millage which was approved in the November 2020 election.​


Documents

Jan. 29, 2020 public meetin​g

Other​
  • What transportation features would you like to see along Scio Church Rd., S. Maple to S. Seventh St.? Online Survey Results 

  • A poll was mailed to addresses along Scio Church Rd. from west of Waltham Drive to Greenview Drive to gauge support for the removal of on-street parking to accommodate bike lanes. Results are provided: ​Parking Removal Postcard Response Summary (PDF)










Project manager:​
Jane Allen, P.E., Civil Engineer IV
734.794.6410 x43678