Stone School Road Sidewalk Project

header image
Skip Navigation LinksHome » Departments » Engineering » Stone School Road Sidewalk Project

​Project Limits

Stone School Sidewalk Map.jpg


​Installation of a sidewalk on the east side of Stone School Road, filling in the sidewalk gap between Packard Road and Eisenhower Parkway





Project Manager                                                            Subscribe for email project​ notifications ​
​Francisca Chan​, P.E.
[email protected]
​734.794.6410 ext. 43701​


Timeline​

Public Engagement – Fall 2023

Public Engagement Meeting – Oct. 30, 2023, 6 p.m.

Construction – Summer 2024

Why is this project being done?

Filling gaps in the sidewalk system is consistent with both Ann Arbor's Moving Together Towards Vision Zero transportation plan and Complete Streets Policy. Providing sidewalks where they currently do not exist can:

  • ​Improve pedestrian safety

  • Encourage active transportation and community health

  • Provide a continuous user experience

  • Provide more transportation options

  • Eliminate the practice of walking along the road and across traffic

Sidewalk gaps throughout Ann Arbor were prioritized for completion based on a system of safety, proximity to pedestrian destinations, roadway classification adjacent to the existing sidewalk gap, resident requests, and other related criteria. For more information, visit the New Sidewalk FAQ webpage. 


Possible impact to residents

  • Temporary lane closure adjacent to sidewalk construction (two-way traffic on Stone School Road will still be maintained).

  • Construction will unavoidably generate dust and noise and many other inconveniences. In addition, you may see utility flags, surveyor stakes, and protection fences located along the roadway which are important to construction and should not be disturbed.

  • Reconstruction of driveway aprons and some landscaping removals within the path of the new sidewalk within city of right of way is required.​

  • The project team will make every effort to avoid property impacts and will coordinate directly with specifically impacted property owners as needed.​

Cost & Funding Source

  • City of Ann Arbor New Sidewalk Millage

  • Township Parcel Owners (only if those parcels are ever annexed)

Documents & Materials​