LynAnne-Arbana Sewer Project

​​

header image
Skip Navigation LinksHome » Departments » Engineering » LynAnne-Arbana Sewer Project

Project l​imits

North of Dexter and West Huron Street, between Lyn Anne Court and Arbana Drive. The project will involve Dexter, Doty​, Westwood Avenue, Maryfield Wildwood Park, Wildwood Avenue, Revena Boulevard, and Arbana Drive. The map below shows the proposed sewer route.

Lyne Anne Sanitary Sewer project map.jpg


Project Manager
Chris Elenbaas, P.E.
[email protected]
​​734.466.4405

For updates on the LynAnne-Arbana Sewer Project

Subscribe for Notification




Timeline

Public Engagement, Design and Bidding
  • Completed
Construction Bids​
  • Winter 2023​
Easement Acquisition
  • Ongoing
Construction
  • Spring/Summer 2024​
Expected road closure timeline
  • Arbana Drive - Spring 2024
  • Doty - Late Summer / Early Fall 2024
  • Westwood Avenue - Late Summer / Early Fall 2024
  • Lane closure along Dexter - Late Fall 2024
  • Maryfield Wildwood Park 

Why is this project being done?

Ann Arbor's LynAnne-Arbana Sewer Project, funded through the Development Offset Mitigation Program (DOM), involves the replacement of 4,300 feet (0.8 miles) of Existing Sanitary Sewer from the Maple Ridge Apartments to Arbana Drive.  The existing sanitary sewer line through the project area was primarily constructed in the 1920s to serve the northwest portion of the city.

This project is being done:

  • To address sewer surcharging and maintenance issues
  • As a continuation of past sewer projects from West Park to Arbana Drive
  • To maintain a key natural corridor ​

​​As part of this project, the city will:​

  • Install the new, larger sanitary sewer and connect it to the existing system.
  • Maintain existing sanitary sewer service throughout the design and construction.
  • Restore areas following construction, including green space and pavement.

Possible impacts to residents

  • Staggered local road closures at Arbana, Westwood/Doty. Access to residences will be maintained.
  • Brief lane closures along Dexter.
  • Sections of Maryfield Wildwood Park will be closed to public.
  • Local road closures, access to residences will be maintained.
  • Tree removals.
  • Construction noise, including generators for bypass pumping as well as some dust and debris in the areas of work.

Cost and funding source

This project is being funded by the City of Ann Arbor Developer Offset-Mitigation Program, which uses developer payments to fund sanitary sewer wet weather capacity improvement projects.​


Documents and materials


October 15, 2020 Project Meeting


June 11, 2020 Informational Meeting Materials