Engineering

LynAnne-Arbana Sewer Project

Skip Navigation LinksHome » Departments » Engineering » LynAnne-Arbana Sewer Project
 
​​

Timeline

  • ​Design – 2020 /21
  • Public Engagement – Spring/Summer 2020
  • Easement Acquisition – ongoing
  • Obtain Construction Bids – Fall 2023
  • Start Construction – Spring 2024

          Project limits

          North of Dexter Avenue and West Huron Street, between Lyn Anne Court and Arbana Drive. The map below shows the existi​ng sewer location. The Lyn Anne – Arbana Sewer is a segment of the Huron West Park trunk sewer which extends from Maple Road to West Park.​

          Lyne Anne Sanitary Sewer project map.jpg

          Why is this project being done?

          The sanitary sewer line in this project area was constructed in the 1920s to serve the northwest portion of the City. A 2017 Sanitary Sewer Improvement Preliminary Engineering report identified that this section of sewer, between Lyn Anne Court and Arbana Drive, needs to be upsized to provide for the long-term operation and maintenance of the sewer system. The total length of this segment is approximately 4,300 feet (0.8 miles)

          Work to be done:

          • Maintain existing sanitary sewer service throughout the design and construction.
          • Install the new sanitary sewer and connect into existing system.
          • Restore areas following construction, including green space and pavement.

          Possible impact to residents:

          • Impacts to residents during the design phase will be minimal. Engineering staff and work crews with vehicles and equipment will be in the sewer vicinity performing preliminary work such as land surveying, soil sampling, taking photos, video-recording and inventorying trees.
          • Construction impacts will be identified as work progresses toward final design. 

          Costs and Funding Source

          This project is being funded by the City of Ann Arbor Dev​eloper Offset-Mitigation Program, which uses developer payments to fund sanitary sewer wet weather capacity improvement projects. 

          Documents and Resources

          Feb. 2021 ​draft plan (PDF)

          Winter 202​0 resident postcard (PDF)

          October, 2020 project meeting

          A second informational meeting on the design of the proposed Lyn Anne-Arbana sanitary sewer was held on Thursday, October 15.  Here are some of the materials from that meeting:

          June 11, 2020 Informational Meeting Materials






           Subscribe to updates for the LynAnne-Arbana Sewer Project.

          ​Project manager:

          Brian Slizewski, PE​
          Larcom City Hall
          Fourth Floor
          301 E. Huron Street
          Ann Arbor, MI
          734.794.6410 ext. 43607