Miller Avenue Improvements Project

​​​​​​​​​

header image
Skip Navigation LinksHome » Departments » Engineering » Miller Avenue Improvements Project

​Miller Avenue, from downtown to Maple Road, will undergo construction in two phases​ to address both utility and transportation needs. 

  • in 2024, during the first phase, from Chapin to Newport, water main will be replaced, stormwater utilities improved and the road repaved.
  • In 2025, during the second phase, from First to Maple, road will be reconfigured to improve biking, walking and mass transit options as well as installing measures to reduce vehicle speeds. ​

In 2021, the city adopted, with the input of thousands of residents, a new comprehensive transportation plan​ that adopted the goals of Vision Zero (no deaths, no serious injuries), to give people of all ages and abilities more travel options while embracing the city's plan to combat climate change. 

This mode of planning is different, as cars have been the driving force of transportation planning for many decades. The community, through the Vision Zero transportation plan​, is rebalancing the scales so that humans, not cars, are the central focus. ​

For this project, please keep in mind:

  • The city has seen in increases in walking and biking as new infrastructure is built.
  • There will be points of conflict between cars, bikes and people at various points. That is the current condition. However, by providing dedicated infrastructure, and reducing speeds, those conflicts become more manageable and safer.
  • Snow removal on bike lanes will continue to be a focus and new equipment is coming online to address it. ​​
  • ​Changes will not negatively impact curbside collection service and instructions on where to put carts will be provided.​

Project limits

Phase 1: Chapin Street to Newport Road​                                                                                  

  • Water Main Replacement​
  • Storm Sewer Improvements
  • Road Repaving

Phase 2: First Street to Maple Roa​d

  • ​​​Combine separate bike lanes into a single two-way cycle track
  • Install speed management devices


Project Manager
‍Jane Allen, P.E.
[email protected]     
734.794.6​410 x43678

                     For updates on the project

                   ​  Subscribe fo​r Notifications

Timeline

Design & Public Engagement

Fall/Winter 2023

Staff have produced a video​ (YouTube) that provides a detailed overview of the project. ​

MIller survey sum​mary (PDF)

Obtain Construction Bids
Jan/Feb. 2024
Construction

Begins late Spring 2024​



​Why this project?

  • Old water mains need replacement as well as the condition of existing infrastructure.
  • Funding is available to make improvements within the Allen Creek watershed for underground detention of storm runoff.
  • The road condition from Newport to Chapin warrants repaving. This section of pavement was not repaved during the 2013 Miller project.
  • Miller Avenue is an all ages and abilities bike corridor, with funding available to upgrade bike lanes. ​​

Potential impacts to residents​ during work

  • Residents in the vicinity will experience noise and dust normally associated with construction.
  • Non-resident traffic will be detoured around the construction zone while local access for residents will be maintained.
  • Water service may be temp​orari​ly interrupted as lines are connected to the new water main. 


Cost & Funding Source

This project is being funded by multiple sources, including City Water Utility and Stormwater Utility Funds, State Transportation funds, County Road Millage Funds, and American Rescue Plan Act (ARPA) funds.