​The City of Ann Arbor is designing and constructing a retrofit of stormwater features for First Sister Lake. Features will include water quality improvements, conveyance modifications, and ecological habitat improvements. This project will have a significant amount of public engagement with the neighborhood and the local community.

After putting out a request for proposal in June 2016, the city has contracted with Environmental Consulting & Technology, Inc. (ECT) to conduct engineering design services for the Sister Lakes Stormwater Retrofit. ECT's work will include historic document review, survey, preliminary design, final design, construction documents, and bid specifications.

Public Engagement

Dates and information will be updated as available.

Meeting #1:
Timeframe:        Thursday, October 13th, 6-7pm
Location:            Dolph Park Observation Dock
                           (Lakeview Dr./Parklake Ave.)
                           ***To be held in Lakewood Elementary School multi-
                           purpose room in case of inclement weather.

Topic:                 Pre-Concept/Information Gathering

Minutes:             Sister Lakes Meeting Minutes 10.13.16 (PDF)

Meeting #2:
Timeframe:       Wednesday, February 8th, 2017 6-7:30pm
Location:           Lakewood School Elementary Multi-Purpose Room
Topic:                Draft Concepts Presentation

Documents:       Sister Lakes Preliminary DRAFT Renderings (PDF)
                           These renderings are NOT final. They represent
                           preliminary DRAFT concepts currently under design
                           consideration. Public comment and input will be
                           welcomed at Meeting #2, as well as by contacting the
                           project managers listed above.

Minutes:             Minutes 2.8.17 (PDF)

Meeting #3:
Timeframe:        Wednesday, April 12th, 2017 6-7:30pm
Location:            Lakewood School Elementary Multi-Purpose Room
Topic:                 Concept Revision

Documents:       First Sister Lake Stormwater Retrofit Concept Design (PDF)

Minutes:             Minutes 4.12.17 (PDF)

Meeting #4:
Timeframe:       Wednesday, June 28th, 2017 6-7:30pm
Location:           First Sister Lake Dock
Topic:                Final Concept/Final Design

Documents:     Final Concept Plan With SW Calcs.pdf
                        First Sister Lake Colored Plan Detail.pdf
                        First Sister Lake Concept Planting Plan.pdf

Meeting #5:
Timeframe:        Thursday, October 19th, 2017 6pm
Location:            First Sister Lake Dock
Topic:                Next Steps – Construction Scheduling

Documents

Contact

Brian Slizewski, PE
Project Manager
Engineering
bslizewski@a2gov.org
734.794.6410 x43607

Jennifer Lawson, CSM
Water Quality Manager
Systems Planning 
jlawson@a2gov.org
734.794.6430 x43735