Project Overview
The purpose of this project was to install a new 8-inch water main on Iroquois Place and on Stadium Boulevard between Iroquois and Packard, in order to replace old water mains and provide improved water quality to the area.
Following the installation of the water main, the asphalt pavement completely replaced on Iroquois, along with the existing speed humps. The two eastbound lanes of East Stadium Boulevard were also be repaved following the water main replacement.
Schedule
The project was substantially completed on July 14, 2009. The contractor will be returning to the site to do some minor repairs and fix some “punch list” items, otherwise the project is complete.