Click to Skip Navigation
Skip Navigation LinksHome > Government > Public Services > Project Management > Projects Under Construction > Glendaloch Circle, Loyola Drive/Colgate Circle, Elmcrest Drive, Anderson Avenue, Clair Circle, Hiawatha Place (GLEACH) Water Main Replacement Project
     Bookmark and Share
Skip navigation links
Project Management
Annual Street Resurfacing Program
East Stadium Bridges Improvement Project
Future Capital Projects
Projects Under Construction
Private Development
Seventh at Washington Pedestrian Refuge Island
Staff Directory
Standard Specifications
Street Millage
Traffic Calming
Traffic Engineering





 Glendaloch Circle, Loyola Drive/Colgate Circle, Elmcrest Drive, Anderson Avenue, Clair Circle, Hiawatha Place (GLEACH) Water Main Replacement Project  

 

Last Updated:  05/14/09

Project Overview

The purpose of this project is to install a new 8-inch water main on Glendaloch Circle, Loyola Drive/Colgate Circle, Elmcrest Drive, Anderson Avenue, Clair Circle, and Hiawatha Place in order to replace old water mains and provide improved water quality to the area. 

Following the installation of the water main, Glendaloch, Elmcrest, Anderson & Hiawatha will have the asphalt pavement completely replaced. Loyola/Colgate and Clair Circle will have the trench asphalt patched to match the existing pavement

Schedule

Work began on Glendaloch Circle the week of April 23rd, and is anticipated to continue through September. 

      • Glendaloch Circle – end of April to mid June
      • Anderson – mid May to end of June
      • Elmcrest – end of May to early July
      • Clair Circle – end of May to early July
      • Hiawatha – July
      • Loyola/Colgate – August

Impact on Traffic & Local Residents

During construction, it will be necessary for our contractor to post temporary “No Parking” signs so that work can proceed in a timely manner. Access to driveways will be maintained during this time, with the exception of some short periods of time when the water main installation crosses in front of your driveway.  When this occurs, the contractor or a City representative will knock on residents’ doors to make sure the driveway does not need to be accessed during that time. 

Garbage collection and mail delivery will be maintained throughout the project. Water service will be maintained during construction, except for brief periods when the new water main is tied in to the existing main, and when house services are transferred to the new main.  Written notice will be given to residents two days before these shutoffs.

Unfortunately, the construction will generate dust and noise, and will cause some inconvenience.  We would like to thank you in advance for your patience and cooperation during the project.  

Progress Updates

Once construction is ready to begin, we will be sending out weekly e-mail updates to anyone interested in receiving them.  If you would like to receive these weekly progress/schedule updates, please send an e-mail to sbryan@a2gov.org and you will be added to the list.

Questions or Concerns?

Contact:

Susan Bryan, Project Manager

734-794-6410 ext. 43631

E-mail: sbryan@a2gov.org

Tim Towles, Inspector - CES
Cell phone: (734) 323-6526
e-mail: ttowles@a2gov.org

 