Project Overview

The City of Ann Arbor 2011 Street Resurfacing Project originally involved the resurfacing of approximately 12 streets located throughout the City. During the course of construction, additional streets were added to the Project.  The project includes the milling and replacement of the asphalt surface, some reconstruction of the road base materials, and the repair and replacement of some existing curbs and sidewalk ramps.  Local residences and businesses on the streets where construction will occur received letters with details several weeks prior to the beginning of the construction in their area.

 

Street List & Schedule

Shown below are the streets included in the 2011 Street Resurfacing Project. A map of these construction areas can be seen clicking here (pdf)

 

 

 STREET  LIMITS                                        

ACTUAL SCHEDULE (2011)

MAJOR STREETS                  
Boardwalk Dr Eisenhower to Victors Way  May 16 – June 12
Victors Way Boardwalk to State St        May 16  - June 12
Beakes St Main St to Summit         May 26 - Sept 19*
Green Rd Glazier Way to Baxter June 15 - Sept 21
Fuller Rd Furstenburg to Huron Pkwy Aug 18 - Aug 27
 Glazier Way Green to Earhart Sept 1 - Sept 22
Division - light resurfacing Huron to Beakes Oct 6 - Oct 17
Miller - patches Newport to Seventh Oct 28
Miller WB Lane - light resurfacing Seventh to Chapin November
 * Two phases with extended break over Art Fair    
RESIDENTIAL STREETS    
Spring St Summit to Sunset May 20 - June 10
Summit/Daniel Ramps intersection June 3 - June 17
Bruce St              Alice to Arborview June 8 - July 5
Longman Ln        Jackson Pl to Fairview Dr Sept 28 - Oct
St. Francis  Nature Cove to E. Stadium July 13 - Aug 11
First St Davis to Koch Aug 20 - Sept 23
Harbal & Leiard Broadway to End July 21 -  Aug 20
Oxford S. University to Hill Sept 14 - Oct 8
Lockridge Dr & Ct     King George to Eisenhower Oct 10 - Nov

 

 

Funding

The 2011 Street Resurfacing Project is funded by the 2007-2011 Street Resurfacing Millage approved by voters in 2006.

 

Questions or Concerns

Elizabeth Rolla, Senior Project Manager

734-794-6410 ext. 43636

erolla@a2gov.org

 